Linkedin Instagram

12 March 2019 – New Techtronics Warehouse achieves Practical Completion

March 12, 2019adminNEWS0

Insight Project Services are very pleased to have been part of the successful completion and hand over of the new Techtronics Warehouse in the Jandakot Airport Precinct today.

We congratulate Chrome Construction for completing the project on time and with little fuss.  It has been a pleasure to work with Matt Jambanis and Nova Nuralda and we look forward to completing the next one – Vulcan Stainless Steel in 4 weeks’ time.

February 2019 – Kincrome achieves Building Permit Approval and Pirone Construction Occupy Site

February 25, 2019adminNEWS, Uncategorized0

Pirone Builders have commenced work on site for the new Kincrome Warehouse and works are progressing well.  Practical Completion is due in September 2019.

January 2019 – Iron Mountain achieves Building Permit Approval and Capstone Construction Occupy Site

February 25, 2019adminNEWS0

Insight Project Services are delivering the new Iron Mountain facility in Perth and are pleased to announce that Capstone Constructions have secured the forward works building permit for the project and occupied site in early February 2019.  Works are well underway and we look forward to another successful project with the Capstone, Linc Property and Gibb Group team.

January 2019 – Oceaneering Expansion achieves Practical Completion

February 25, 2019adminNEWS0

The expansion of the existing Oceaneering Workshops at Jandakot achieved PC in January 2019 with PS Structures delivering another quality asset for Jandakot City Holdings.  We hope Oceaneering enjoy the new facility.

December 2018 – IPS Appointed to Schenck Process Warehouse and Workshops Project

December 6, 2018adminNEWS0

We are pleased to announce that Jandakot City Holdings (JCH) appointed Insight to the role of Project Manager and Superintendent for the new Schenck Process Warehouse, Office and Workshops.  The project consists of 1,300sqm of new office space, 10,560sqm of Workshop and Warehouse space, 144sqm of wash/blasting bays, parking for 218 vehicles and approximately 26,000sqm of external concrete hardstand pavements.  PS Structures have been appointed as the Design and Construct Builder and the project was kicked-off on 3 December 2018 with Practical Completion scheduled for 20 December 2019.

November 2018 – Forrest Hall Stage 2 achieves development approval

November 27, 2018adminNEWS0

After a long process of design and consultation, Forrest Hall Stage 2 was unanimously recommended for development approval by the City of Perth Local Development Assessment Panel on 22 November 2018.  Congratulations to all involved and we can’t wait to proceed with the next phase of the project.

November 2018 – IPS appointed Project Manager for Equinix

November 27, 2018adminNEWS0

IPS are proud to have been selected as the Project Manager for the new Equinix Data Centre in Shenton Park Perth.  IPS were selected for our specific experience and knowledge of services and recent work on data exchange facilities and complex engineering projects.  Our client – Equinix – is an American multinational company headquartered in Redwood City California, that specialises in internet connection and related services.  It is a global colocation data centre provider, leading by market share, operating 175+ data centres in 44 metropolitan areas in 22 countries on 5 continents.  The project will be delivered in the second quarter of 2019 and we look forward to great success with Equinix and their team.

The Vale Bar and Brasserie opens 4pm 22 November

November 28, 2017adminNEWS0

The Vale Bar and Brasserie on the corner of Beeliar Drive and Durnin Avenue Yangebup achieved Practical Completion on the 13th of Nov 2017 and opened its doors to the public at 4pm on the 22nd Nov 2017 (3 weeks ahead of schedule).  IPS fulfilled the role of Project Manager and Superintendent and would like to extend its thanks to the Builder (Perkins TPD) and the entire consultant team for their efforts in achieving completion ahead of schedule and for the fantastic outcome achieved by all.

We look forward to our first beer before the Silly Season strikes.

Redcastle achieves practical completion 31 March 2017

April 3, 2017adminNEWS0

BGC achieved Practical Completion of the Redcastle Apartment project on 31 March 2017 and we are proud to have been a part of the project and congratulate BGC on a fantastic job and Handle Property Group on another successful development.

IPS completes new St Vincent de Paul Head Office, Depot and Retail Outlet

November 17, 2016adminNEWS0

On 7 November 2016 a significant milestone occurred for the St Vincent de Paul Society of WA – IPS successfully handed over the new Vinnies State Headquarters in Canning Vale.  Practical Completion was reached (ahead of schedule) and Vinnies will now be able to expand their already broad range of services to help disadvantaged people in our community.  IPS commenced on the project more than three years ago with a Business Case, Development Feasibility, Site Acquisition Services and then Project Management and Superintendent services for the delivery stage.  The project has been a labour of love and we have enjoyed working with the Vinnies team and seeing the project through from inception to completion.